General Assist Technical Reference

Wall-Mounted Split Installation Guide

ASTG09KMCB / ASTG12KMCB
For approved AOTG09KMCB / AOTG12KMCB R32 outdoor units
R32 flammable refrigerant: Installation, pressure testing, evacuation and service work must be completed by qualified personnel using R32/R410A-rated equipment. Remove ignition sources, ventilate the work area and use an R32-compatible leak detector.
KMCB highlights: Built-in WLAN, six indoor piping directions, dry-nitrogen pressure test at 4.15 MPa, vacuum target of 65 Pa / 500 microns and a revised wireless remote-controller test-run process.

1. Quick specifications

ItemRequirement
RefrigerantR32
Liquid pipe6.35 mm (1/4 in), minimum wall thickness 0.8 mm
Gas pipe9.52 mm (3/8 in), minimum wall thickness 0.8 mm
Maximum pipe length20 m
Maximum height difference15 m
Additional refrigerantNone required up to 20 m
Maximum total charge850 g
Cooling range10°C to 46°C
Heating range-15°C to 24°C
Power supply1 phase, 240 V, 50 Hz; operating range 198–264 V
Power cable1.5 mm², 2 conductors plus earth
Interconnection cable1.5 mm², 3 conductors plus earth
Model 09 breaker10 A
Model 12 breaker16 A reverse-cycle model
Earth leakage breaker30 mA, 0.1 second or less
Short pipework: Pipe runs shorter than 3 m may transfer outdoor-unit sound to the indoor unit and increase perceived operating noise.

2. Indoor-unit installation

ClearanceMinimum
Above unit63 mm
Left side70 mm
Right side130 mm
Floor to indoor unit1.8 m
Remote-controller rangeMaximum 7 m
Built-in WLAN: Record or retain the WLAN label located inside the front panel beside the WLAN indicator. Keep the label with the WLAN setting manual for customer handover.
Human sensor: Approximate detection range is 7 m, 90° vertically and 100° horizontally. Keep heaters and large objects outside the detection area.

Six piping directions

Rear Right Bottom Left-bottom Left Left-rear
1Choose a strong, level wall with unrestricted airflow, suitable drainage and adequate WLAN reception.
2Secure the wall-hook bracket level using at least five large fixing screws.
3Cut a 65 mm wall hole with the outside edge 5–10 mm lower than the inside edge.
4Fit a wall pipe and wall cap to prevent wiring contacting raw metal.
5For left-side routes, transfer the drain hose and drain cap and refit the retaining screw.
6Keep the drain hose below the refrigerant pipes and maintain continuous fall.
7Engage the upper hooks first, then push the lower fittings onto both lower hooks.
Drainage: Do not lift the drain hose, create waves or submerge its end. Apply freeze protection where the hose may be exposed below 0°C.

3. Outdoor-unit installation

SideMinimum clearance
Rear10 cm
Left10 cm
Right25 cm
Front20 cm
Above60 cm
Below5 cm
  • Mount on a strong, level stand and keep tilt below 5°.
  • Secure against strong wind.
  • Do not install directly on the ground.
  • Keep at least three horizontal directions open where possible.
  • Do not use drain pipes or caps where freezing may block drainage.

4. Flare connections

Pipe sizeTorque
6.35 mm16–18 N·m
9.52 mm32–42 N·m
Use R32/R410A-compatible flare tools. Maintain a bend radius of at least 70 mm and do not bend the same section more than three times.

5. Pressure test

Dry nitrogen only. Never use refrigerant, oxygen, compressed air or flammable gas to pressure-test the system.
1Confirm both service valves are closed and power remains isolated.
2Introduce dry nitrogen to both liquid and gas lines.
3Pressurise to 4.15 MPa.
4Leak-test all indoor and outdoor connections.
5Confirm the pressure does not decrease.

6. Vacuum and drying process

1Connect a clean R32/R410A manifold and vacuum pump.
2Evacuate to -0.1 MPa or 65 Pa / 500 microns.
3Continue vacuum operation for at least 15 minutes.
4Close the manifold, stop the pump and stand for 1–2 minutes. Confirm the gauge does not rise.
5Crack the 3-way valve until pressure reaches approximately 0.1–0.2 MPa, then disconnect the hose.
6Fully open both service valves and tighten all caps.
CapTorque
1/4 in blank cap20–25 N·m
3/8 in blank cap20–25 N·m
Charging-port cap12.5–16 N·m

7. Electrical wiring

Match terminals 1, 2 and 3 between indoor and outdoor units and connect protective earth. Clamp cables by the outer sheath.
Terminal screwTorque
M3.50.8–1.0 N·m
M41.2–1.8 N·m
M52.0–3.0 N·m
Keep demand-control wiring separated from the power and interconnection cables to prevent electrical interference.

8. Test run and commissioning

Wireless remote controller

  1. Connect power and wait at least one minute.
  2. Press START/STOP.
  3. Press the recessed TEST RUN button using a ballpoint pen or similar object.
  4. Press START/STOP to end the test.

Indoor-unit button

Hold MANUAL AUTO for more than 10 seconds. The OPERATION and TIMER lamps flash together. Stop the test using START/STOP on the remote controller.
Commissioning checkDone
Remote-controller buttons and display operate correctly
Indicator lamps operate correctly
Airflow louvres operate correctly
Drainage test completed with no leaks
No abnormal noise or vibration
No refrigerant leakage detected
WLAN label recorded and setting manual retained
Customer shown operation and filter maintenance

9. Optional controls

OptionReference
Wired remote controllerUTY-RVNYN / UTY-RNNYN; communication kit required
Simple remote controllerUTY-RSNYN; communication kit required
External connect kitUTY-XWZXZ5
Communication kitUTY-XCBXZ2
Final handover: Leave the installation, operating and WLAN setting manuals with the customer. Record any changed settings and confirm app setup requirements.
Based on Fujitsu General indoor installation manual Part No. 9333005201-02 and outdoor installation manual Part No. 9320394004-04. This simplified field reference does not replace the complete manuals, equipment rating labels or current Australian and New Zealand regulations.